NOTICE These resolutions, summaries of which are published herewith, have been adopted by the County Legislature on …

NOTICE

These resolutions, summaries of which are published herewith, have been adopted by the County Legislature on August 1, 2019, and the validity of the obligations authorized by such resolution may be hereafter contested only if such obligations were authorized for an object or purpose for which the COUNTY OF ORANGE, New York, is not authorized to expend money or if the provisions of law which should have been complied with as of the date of publication of this Notice were not substantially complied with, and an action, suit or proceeding contesting such validity is commenced within twenty days after the publication of this Notice, or such obligations were authorized in violation of the provisions of the Constitution.

Kelly A. Bradley

Deputy Clerk of the Legislature

RESOLUTION NO. 200 OF 2019

BOND RESOLUTION DATED AUGUST 1, 2019

BOND RESOLUTION OF THE COUNTY OF ORANGE, NEW YORK, AUTHORIZING THE PREPARATION OF SURVEYS, PRELIMINARY AND DETAILED PLANS, SPECIFICATIONS AND ESTIMATES NECESSARY FOR THE CONSTRUCTION OF A BUILDING EXPANSION AT THE COUNTY SHERIFF'S OFFICE, STATING THE ESTIMATED MAXIMUM COST THEREOF IS $350,000, APPROPRIATING SAID AMOUNT THEREFOR, AND AUTHORIZING THE ISSUANCE OF $350,000 BONDS OF THE COUNTY TO PAY THE COST THEREOF

object or purpose: the preparation of surveys, preliminary and detailed plans, specifications and estimates necessary for planning the construction of a building expansion at the County Sheriff's Office, all as more particularly described in the County's 2019 Capital Plan, as amended.

period of probable usefulness: five (5) years

amount of obligations to be issued: $350,000

RESOLUTION NO. 201 OF 2019

BOND RESOLUTION DATED AUGUST 1, 2019

BOND RESOLUTION OF THE COUNTY OF ORANGE, NEW YORK, AUTHORIZING THE PREPARATION OF SURVEYS, PRELIMINARY AND DETAILED PLANS, SPECIFICATIONS AND ESTIMATES NECESSARY FOR THE CONSTRUCTION OF A SNOW REMOVAL EQUIPMENT BUILDING, STATING THE ESTIMATED MAXIMUM COST THEREOF IS $92,250; APPROPRIATING SAID AMOUNT THEREFOR, INCLUDING $83,025 EXPECTED TO BE RECEIVED FROM THE UNITED STATES, AND $4,612 EXPECTED TO BE RECEIVED FROM THE STATE OF NEW YORK; AND AUTHORIZING THE ISSUANCE OF $4,613 BONDS OF THE COUNTY TO FINANCE THE BALANCE OF SAID APPROPRIATION

object or purpose: the preparation of surveys, preliminary and detailed plans, specifications and estimates necessary for planning the construction of a snow removal equipment building, all as more particularly described in the County's 2019 Capital Plan, as amended.

period of probable usefulness: five (5) years

amount of obligations to be issued: $4,613

RESOLUTION NO. 202 OF 2019

BOND RESOLUTION DATED AUGUST 1, 2019

BOND RESOLUTION OF THE COUNTY OF ORANGE, NEW YORK, AUTHORIZING THE PREPARATION OF SURVEYS, PRELIMINARY AND DETAILED PLANS, SPECIFICATIONS AND ESTIMATES NECESSARY FOR THE MASTER PLAN UPDATE AND PAVEMENT MANAGEMENT PROGRAM AT THE ORANGE COUNTY AIRPORT, STATING THE ESTIMATED MAXIMUM COST THEREOF IS $543,192; APPROPRIATING SAID AMOUNT THEREFOR, INCLUDING $488,872 EXPECTED TO BE RECEIVED FROM THE UNITED STATES, AND $27,160 EXPECTED TO BE RECEIVED FROM THE STATE OF NEW YORK; AND AUTHORIZING THE ISSUANCE OF $27,160 BONDS OF THE COUNTY TO FINANCE THE BALANCE OF SAID APPROPRIATION

object or purpose: the preparation of surveys, preliminary and detailed plans, specifications and estimates necessary for the Master Plan Update and Pavement Management Program at the Orange County Airport, all as more particularly described in the County's 2019 Capital Plan, as amended.

period of probable usefulness: five (5) years

amount of obligations to be issued: $27,160

RESOLUTION NO. 203 OF 2019

BOND RESOLUTION DATED AUGUST 1, 2019

BOND RESOLUTION OF THE COUNTY OF ORANGE, NEW YORK, AUTHORIZING THE REHABILITATION OF THE TRANSIENT APRON AT THE ORANGE COUNTY AIRPORT, STATING THE ESTIMATED MAXIMUM COST THEREOF IS $100,000; APPROPRIATING SAID AMOUNT THEREFOR, INCLUDING $90,000 EXPECTED TO BE RECEIVED FROM THE UNITED STATES AND $5,000 EXPECTED TO BE RECEIVED FROM THE STATE OF NEW YORK; AND AUTHORIZING THE ISSUANCE OF $5,000 BONDS OF THE COUNTY TO FINANCE THE BALANCE OF SAID APPROPRIATION.

object or purpose: the rehabilitation of the transient apron at the Orange County Airport, all as more particularly described in the County's 2019 Capital Plan, as amended.

period of probable usefulness: ten (10) years

amount of obligations to be issued: $5,000

RESOLUTION NO. 204 OF 2019

BOND RESOLUTION DATED AUGUST 1, 2019

BOND RESOLUTION OF THE COUNTY OF ORANGE, NEW YORK, AUTHORIZING THE PREPARATION OF SURVEYS, PRELIMINARY AND DETAILED PLANS, SPECIFICATIONS AND ESTIMATES NECESSARY FOR THE REHABILITATION AND EXPANSION OF APRON A AT THE AIRPORT, STATING THE ESTIMATED MAXIMUM COST THEREOF IS $134,750; APPROPRIATING SAID AMOUNT THEREFOR, INCLUDING $121,275 EXPECTED TO BE RECEIVED FROM THE UNITED STATES, AND $6,737 EXPECTED TO BE RECEIVED FROM THE STATE OF NEW YORK; AND AUTHORIZING THE ISSUANCE OF $6,738 BONDS OF THE COUNTY TO FINANCE THE BALANCE OF SAID APPROPRIATION

object or purpose: the preparation of surveys, preliminary and detailed plans, specifications and estimates necessary for planning the rehabilitation and expansion of Apron A at the Airport, all as more particularly described in the County's 2019 Capital Plan, as amended.

period of probable usefulness: five (5) years

amount of obligations to be issued: $6,738

RESOLUTION NO. 205 OF 2019

BOND RESOLUTION DATED AUGUST 1, 2019

BOND RESOLUTION OF THE COUNTY OF ORANGE, NEW YORK, AUTHORIZING THE CONSTRUCTION OF A BULK HANGAR AT THE COUNTY AIRPORT, STATING THE ESTIMATED MAXIMUM COST THEREOF IS $1,452,940; APPROPRIATING SAID AMOUNT THEREFOR, INCLUDING $1,307,646 EXPECTED TO BE RECEIVED FROM THE STATE OF NEW YORK; AND AUTHORIZING THE ISSUANCE OF $145,294 BONDS OF THE COUNTY TO FINANCE THE BALANCE OF SAID APPROPRIATION.

object or purpose: the construction of a bulk hangar at the County Airport, all as more particularly described in the County's 2019 Capital Plan, as amended.

period of probable usefulness: twenty-five (25) years

amount of obligations to be issued: $145,294

A complete copy of the Bond Resolutions summarized above shall be available for public inspection during normal business hours at the office of the Clerk of the Orange County Legislature, in Goshen, New York.

Dated: August 7, 2019

Goshen, New York #97314

Posted 12/31/1969